As a project manager, you estimate a task to take two days. Your team actually took five days to complete the task. What describes the tendency that caused you to underestimate the time for the task?

Q: As a project manager, you estimate a task to take two days. Your team actually took five days to complete the task. What describes the tendency that caused you to underestimate the time for the task?

  • Feedback fallacy 
  • Opinion bias 
  • Planning fallacy 
  • Pessimism bias