As a project manager, you’re implementing the ROAM technique for a new risk. You figure out how to work around the risk so it will no longer be a problem. Which ROAM action did you take?

Q: As a project manager, you’re implementing the ROAM technique for a new risk. You figure out how to work around the risk so it will no longer be a problem. Which ROAM action did you take?

  • Resolved 
  • Owned
  • Accepted
  • Mitigated