Q: Imagine you are a project manager for a software company. Your team plans to develop a new learning management system (LMS) for a local school district by the end of the quarter. Which of the following factors can potentially push back your release plan date? Select all that apply.
- The Product Owner expands the project to include two additional school districts.
- A member of your development team leaves to take a new job.
- Your team realizes an epic will take more time to complete than anticipated.
- The school district increases the project budget and provides additional resources.