As a project manager, you’re identifying task dependencies. Task B cannot start until Task A is complete. Which type of dependency does this situation represent?

 

Q: As a project manager, you’re identifying task dependencies. Task B cannot start until Task A is complete. Which type of dependency does this situation represent?

  • Finish to Finish (FF) 
  • Start to Start (SS)
  • Start to Finish (SF) 
  • Finish to Start (FS)