Q: Which of the following circumstances indicates that the project is approved to move forward?
- The stakeholders state the cost of the project outweighs the value it brings to the organization.
- The project manager finishes the project’s deliverables and milestones.
- The project sponsor and key stakeholders sign off on the project charter.
- The finance department approves the budget and the team members have been selected