Q: Consider the following scenario: The Director of Product requests that the project manager do what they can to finish the project early. However, the Director states that they cannot spend any additional funds. Using the triple constraint model, what trade-off could the project manager use to meet the Director of Product’s request?
- Change the project scope
- Change the budget
- Change the project goal
- Change the team
